A schedule of renovations of South Campus parking lots has been announced. The following lots will be closed to allow for the milling, repaving and restriping of each:

Lot Closed for Paving Dates Of Work
Sherman Lot May 10 through May 31
Diefendorf Lot June 1 through June 22
NFTA Park & Ride Lot June 28 through July 19

Where To Park During Paving

Parking lot occupancy will be extremely low during the renovation times, and commuters will be able to find parking in several nearby lots. Parking and Transportation Services will place wayfinding signage to direct the community to the Michael-Farber and Clark Lots during the construction period.

The Sherman and Diefendorf Lots, which are adjacent to each other, will not be closed simultaneously; work will only commence once the other is reopened.

Contact For Help or Questions

Customer Service Walk-in Center
1Capen
North Campus
Monday — Friday, 8:30 a.m. to 4:30 p.m.

Proof of Daily Health Check is required for in-person services. Reservations are required during peak service periods. Visit the 1Capen website for available services and reservation updates. 

 

Administrative Offices
106 Spaulding Quadrangle
North Campus
Tel: 716-645-3943
Email: parking@buffalo.edu
Email: transportation@buffalo.edu