Decommissioning UB's Buffalo Materials Research Center
Frequently Asked Questions
Published
December 4, 2012
What does “decommissioning” of a nuclear facility mean?
The activities of the U.S. Nuclear Regulatory Commission (NRC)
include decommissioning nuclear facilities.
Decommissioning is the process of safely closing a nuclear power
plant (or other facility where nuclear materials are handled) to
retire it from service after its useful life has ended.
This process primarily involves decontaminating the facility to
reduce residual radioactivity and then releasing the property for
unrestricted or (under certain conditions) restricted use. This
often includes dismantling the facility or dedicating it to other
purposes. Decommissioning begins after the nuclear fuel and loose
radioactive waste are removed.
For more information on the NRC’s decommissioning process,
go to http://www.nrc.gov.
What is the scope of the University at Buffalo project?
UB is in the final stage of a process to remove contaminated
materials from its former nuclear reactor facility (known as the
Buffalo Materials Research Center), demolish the building and
verify decontamination of the soil around and underneath the
site.
The Buffalo Materials Research Center (BMRC) is located on
UB’s South Campus. See campus map: http://www.buffalo.edu/buildings/building?id=bmrc
During this final stage of decommissioning, the university will
safely remove from the building equipment and materials that were
contaminated with radioactive material when the facility was in
operation. The building will then be demolished and
water tanks and contaminated soil underneath it will be
removed.
When the process concludes in 2014, the site will be free of
radioactive contamination, and it will be returned to a green
field.
Similar projects were undertaken in recent years at Cornell
University, the University of Michigan and other university-based
research reactor facilities.
Is there still nuclear fuel in the facility
No. The facility’s radioactive fuel was completely
removed in 2005 as part of the facility’s decommissioning
process.
Why is UB taking down the facility?
The facility’s nuclear reactor has not been in operation
1994 and the facility’s radioactive fuel was completely
removed in 2005. The university was not performing
sufficient research involving nuclear materials to warrant
maintaining such a facility.
UB received permission from federal and state authorities to
take down the building and return the site to a green
field.
What was the facility used for?
It was built in 1961 and was mainly used for isotope production
and materials testing. It was last operated in 1994.
Why not rehabilitate and reuse the facility instead of taking it down?
This option was considered by the university. An extensive
analysis determined it is far too costly to rehabilitate the
facility. The building’s structural components would need to
be scraped and nearly completely torn away before the facility
could be rebuilt. It is more efficient to take down the
building.
What are the risks to the campus and the community as UB removes materials contaminated by radiation?
The health risks are minimal. A person passing by the
demolition site will not receive any additional radiation exposure
than what occurs normally in the environment.
What kind of contaminated materials are being removed from the facility?
Research equipment used when the facility was in operation will
be removed as well as the facility’s heating and cooling
system. Water from reactor tanks and the tanks themselves
also will be removed. Steel and concrete from the demolished
facility will be removed, as will contaminated soil and bedrock
from the facility site.
There are six underground storage tanks ranging in size from 250
to 10,000 gallons and one 10,000 gallon above-ground tank. These
tanks will be emptied and sent for disposal. Onsite cleaning may be
performed prior to transportation depending on contamination levels
and waste costs.
What will be done with contaminated materials removed from the facility and site?
All contaminated waste will be safely shipped to appropriate
disposal facilities outside of New York State.
Is there contamination of the groundwater surrounding the site?
No. An analysis of the site has determined there is no
contamination to groundwater underneath the building.
Is there radioactive contamination of the site outside the building’s boundaries?
No. An analysis of the site did not discover any radioactive
contamination beyond the boundaries of the physical building.
What safety measures are in place?
All activities will be performed under the strict NRC
decommissioning guidelines for which the university will be
responsible.
When radioactive materials are removed from the building and
staged outside for transport, health physicists will ensure that
radiation levels are within federal guidelines. When work
activities inside facility are undertaken, air and water from the
work site will be monitored and/or filtered per the requirements of
the decommissioning plan.
Will there be any airborne discharges of radioactivity or releases of dust during the project that could pose an offsite hazard?
No. Except for demolition of the building, all air discharged
from the facility will be filtered as necessary in a manner similar
to an asbestos work area.
What types of construction activities and noise are expected from this project?
Except for the demolition of the building, the process will go
almost unnoticed even by faculty, staff, students and community
members who are within sight of the facility. There will be
occasional trucks making deliveries and pickups, mobilization of
construction trailers, etc. The university will take steps to
minimize noise, dust and vibration resulting from the
building’s demolition.
Who will oversee the day-to-day decommissioning process?
The decommissioning project will be a campus-led project managed
by UB's Facilities Planning and Design group. Special consultants
will be brought in to handle specific phases of work for which
little local expertise exists.
How does the NRC regulate and control the decommissioning process?
The NRC’s inspector will be on site frequently and during
significant project milestones to ensure that guidelines are being
met.
To what standard will the BMRC site be cleaned?
After the building is dismantled and all contaminated materials
are removed, the site will be returned to a green field. The
NRC will perform a final inspection and declare the site is clean
and in compliance with guidelines developed by the NRC and the
Environmental Protection Agency.
What is the cost for this project?
New York State provided funding to UB’s capital plan to
pay for the project. There is no funding from other sources.
It is estimated that the entire decommissioning process will
cost about $20 million.
How will the community be informed and involved in the decommissioning process?
The university will hold public meetings to update the campus
and community about progress made during decommissioning.
UB’s Office of University Communications will notify the
public of these meetings through news releases distributed to news
media, mailings to neighborhoods near the South Campus and notices
posted to university websites.